4.1 Submittal Schedule

4.1.1 The Constructor shall schedule submittal of Shop Drawings and Product Data to the Design Professional so that no delays will result in delivery of materials and equipment, advising the Design Professional of priority for checking of Shop Drawings and Product Data; a minimum of two weeks shall be provided for this purpose.

4.2 Construction Review

4.2.1 Each Submittal shall bear a stamp or specific indication that the Submittal complies with the Contract Documents and Constructor has satisfied its obligations under the Contract Documents with respect to Constructor’s review and approval of that Submittal. Each Submittal shall bear the signature of the representative of Constructor who approved the Submittal, Constructor’s name, Owner’s name, Project number, title, item name and specification section number.

4.3 Expertise & Experience

4.3.1 The Constructor represents and warrants that all Shop Drawings shall be prepared by persons and entities possessing expertise and experience in the trade for which the Shop Drawing is prepared and, if required by the Design Professional or applicable Laws, by a licensed engineer or other design professional.